Motorcycle Shelter 

Work included: 

Ground Penetration Radar Survey & establishment of existing services. 
Site clearance & excavation of existing kerb-lines. 
Excavate for foundation bases & dispose of spoils off site. 
Erection of timber formwork & suspend holding down bolts. 
Installation of steel fabric mesh and reinforcing bar. 
Cast new concrete pad foundations. 
Installation of Broxap shelter. Approximately 39m in length with the capacity to hold 32 motorcycles. 
Lay new HB2 kerbs around new shelter. 
Install new service ducting from feeder pillar and provide electric power supply to new motorcycle shelter. 
Connect shelter down pipe to storm water pipe and run to new filter drain constructed in adjacent verge 
Reinstate car park surfaces with asphalt & over-band patches. 
Lay new thermoplastic line markings to motorcycle bays. 
Hard and soft landscaping to the surrounding verges. 

Info: 

Duration: 
8 Weeks 
Client: 
Amey Defence Services Ltd 
Value: 
£249,000.00 

Innovation: 

Our aim was to construct a bespoke covered motorcycle parking area to assist with the reduction of cars on site, improve customer experience and assist with improvements to the working headquarters environment. In full compliance with RIBA Stage 4. 